The Massey Mayhem;
let’s build a bridge!
Having planned to build a new ten lane bridge over the
Fraser River, the BC Government has yet to provide a business case for the
proposal. In the meantime, a $3 Billion price tag has been proposed for the
bridge and removal of the existing Massey tunnel. Now, with the possibility of
LNG ships passing under the bridge, Port Metro Vancouver (PMV) has stated that
they need an additional 8M (24 feet) of height for the bridge. This will not
only increase the cost of the bridge, it will add to the difficulty of locating
off-ramps for Steveston and Ladner.
Why build a bridge?
The primary reason to replace the tunnel is to allow PMV to
bring deeper hull ships through to the Surrey Fraser docks. The tunnel has had
$20 Million in seismic upgrades in the past ten years and is known to be
serviceable for a long time. Why is it that we are even considering replacing
the tunnel? It can be an effective part of the solution to the “congestion”
experienced in the Lower Mainland. As long as the tunnel is there it will
restrict access to both the Oak Street and Knight Street corridors.
Wait, what, why not a
bridge?
That may sound like a self defeating notion and is quite likely
why a large part of the population is in support of the bridge. It will be more
effective at getting cars across the Fraser. However, those same travelers coming from South Surrey and White
Rock are then being restricted when crossing into the Vancouver core. The
proposed bridge does nothing to solve the traffic nightmare at the Oak Street
and Knight Street corridors. Both of these bridges into Vancouver can be as
congested as the approach to the tunnel. Once the government commits to
building the Massey bridge there will not likely be any funds, desire -or ability-
to deal with this “congestion.”
What’s all at stake?
What we haven’t been told is that replacing the tunnel is
only a fraction of the cost; there is still more at stake. The Metro Vancouver
Water District apparently has a 32” water main near the tunnel that serves
Delta. This water main would also have to be removed in order to achieve the
desired depth. No cost accounting has
been done for moving the water main. It is not clear at this time if Hydro also
has any utilities that need to be moved.
The additional one
time dredging costs to lower the river bottom to the 13.5 M (44 feet) depth
proposed by the Provincial Government is estimated to be $175 Million. The new
ongoing annual cost for the deeper
proposed dredging depth has not been determined or accounted for. Presently
Port Metro Vancouver pays $15 Million to dredge the river annually to a depth
of 11.5M. Only $10 Million of that cost is recovered by the sale of sand and
the remaining sand has to be disposed of at cost.
There is more to the dredging than a financial cost. A
report called “Sediment management in (the) Lower Fraser River (March 20, 2010,
Michael Church) states that to avoid “serious adverse affects to fish population…
a long term management program should be initiated before additional sediment
is removed by gravel or sand dredging”. No
such plan has been undertaken or, at least, made public.
So what’s all the
fuss?
The Fraser River estuary has been designated a RAMSAR site
by the UN. The estuary is considered an area of international ecological
importance for migratory birds and fish species. The removal of the tunnel and
increasing shipping traffic along the Fraser River is just one of the proposals
that PMV has on the table. An additional 3 birth container terminal is being
planned at the mouth of the Fraser and LNG shipping is being planned. As well, soft (thermal) coal is now being
shipped from the States through the Surrey Fraser Docks and Texada Island. Only
ad-hoc environmental planning has been done for these projects and no
full-scale overview has been required by any of our environmental agencies.
So what else is
involved?
The latest word on LNG is that it will be handled in and
shipped from 80 acres of the Tsawwassen lands. Nicely done PMV! Now you can
honestly say it is beyond your jurisdiction and wash your hands of the whole
affair. No pesky environmental undertakings needed. The leadership of the
Tsawwassen First Nation says it’s committed to ensuring best practices are used
in all aspects of this proposal. How this will be achieved was not made clear. Chief
Bryce Williams, the youthful leader said that “they would work with their
partners to ensure best practices”`. The proposal will be voted on by the
members of the band in mid December. No other public input will be required.
This has to be a coup for Robin Silvester and PMV. What a way to circumnavigate
all those environmental concerns!
Promises,
promisezzzzz!
When Premier Christie Clark announced the bridge proposal
she stated that “a new bridge will open the corridor to future rapid transit
options”. The operative word here being “future”. The failed Translink
plebiscite showed no improvements or transit offerings to the South Delta area.
One can only assume that with the proposed bridge costs it will be a long way
into the future before funds are available for those “rapid transit options”.
Rapid transit is generally driven by population growth. It is clear from the Provincial Government
initiative to weaken the Agricultural Land Reserve (ALR) how this will affect Delta.
A weakened ALR puts South Delta
farmlands at risk. In most parts of the world Agricultural land is at a
premium. Obviously the present
Provincial Government does not see it this way. As well, the CEO of Port Metro
Vancouver, Robin Silvester, responded to these concerns by stating that we
could “import our food”.
Why would any business person consider it prudent to rely on
imports for our food needs? The South Delta farmlands have some of the best
climatic conditions in Canada. The food grown here serves a large local
population and shipping to this market is environmentally effective. We have a
finite agricultural land base. We would be weakening our ability to be self
reliant by reducing any of our agricultural lands, especially those in South
Delta. If recent increases in food prices can be attributed to problems with
agriculture in California we need to protect our agricultural interests. Anything
less does not serve our self interest. No matter how much PMV wants to create a
“Gateway to the Pacific”.
The fly in the
ointment.
Lastly, why are the needs of Port Metro Vancouver driving
the transportation planning process for the Greater Vancouver Regional District
(GVRD)? How is it that this Federal Crown Corporation has the power to
influence Regional decisions of this magnitude without being made accountable?
As a Federal Crown Corporation, the residents of Canada are
PMV`s largest group of stakeholders. We need to ensure that PMV stays true to
their vision; "inspiring support from our customers and from
communities locally and across the nation," as well as their mission
statement: "To lead the growth of Canada's Pacific Gateway in a manner
that enhances the well-being of Canadians and inspires national pride.
If the community of Delta were polled about Port Metro's
various undertakings on the Fraser, the response would be very interesting. I
very much doubt that "inspiring support and... national pride" or
"enhancing the well-being of Canadians" would ring true for anyone in
Delta.
Why are BC residents
being asked to pay the price?
“As
a port authority under the Canada Marine Act, Port Metro Vancouver is mandated
to facilitate Canada's trade, while ensuring environmental protection and
safety”. Under the direction of CEO Robin Silvester they seem to be
concentrating on the trade aspects and not the environmental protection or
safety. Sadly ‘facilitating Canada’s trade’ leads to BC residents paying for
and living with second rate transportation solutions. Surely our Premier
Christy Clark and her government can demand more than that from the Federal
Government. As premier of this province her position should be to represent BC
in Ottawa; not to present Ottawa’s position to BC.